HRS §180-9
Renewal of petition to create
This section says when you can file a new petition for the same proposed district after the state land department rejected it. You must wait six months from the department's decision. After that, you may file again the same way as before.
landownerstenants
The statute, as written — Renewal of petition to create
After six months after the date of a determination by the department of land and natural resources that the operation of a proposed district would not be administratively practicable and feasible, subsequent petitions covering the same or substantially the same territory may be filed as aforesaid.