← Back to search

HCC §5-8-5

Final inspection after all permitted work is done

Read the official text at hawaiicounty.gov ↗

This section says the final inspection happens after all work under the permit is finished. The contractor on record can ask for a certificate of inspection, but only if all required construction fees are paid.

contractors

The ordinance, as written (Hawaiʻi County) — Final inspection

A copy, taken August 21, 2026. The version published by Hawaiʻi County is the one that governs, and it may have changed since. Check it before relying on anything here.

(a) The final inspection shall be made after all work required by the permit is completed. (b) A certificate of inspection may be issued upon request by the contractor on record, provided all fees required by the construction code have been satisfied. (2020, ord 20-61, sec 2.) 5-8-5
Read the official text at hawaiicounty.gov ↗as published Jul 16, 2026our copy taken Aug 21, 2026

Published by the County of Hawaiʻi Office of the County Clerk.

LawTrove is not legal advice. The summary above is a computer-generated restatement — the authoritative text is the official version linked above.