MCC §16.25.107
Submittal documents
Read the official text at library.municode.com ↗This section explains what plans and documents you must give the county when applying for a building permit. It covers who must prepare the plans, what the plans must show, how the county reviews them, and what happens if you change them. It also covers special rules for fire systems, balconies, and registered model home plans.
businessescontractorsdevelopershomeownerslandlords
The ordinance, as written (Maui County) — Submittal documents
A copy, taken August 21, 2026. The version published by Maui County is the one that governs, and it may have changed since. Check it before relying on anything here.
107.1 General. With each application for a building permit construction documents shall be submitted
to the building official. Construction documents shall be prepared by a registered
design professional:
1. As required by Hawaiʻi Revised Statutes, chapter 464 and related Hawaiʻi Administrative
Rules.
2. For new one- and two-family dwellings.
3. For a change of occupancy classification.
4. For work started or completed prior to obtaining a building permit.
5. For additions, alterations, and repairs 400 square feet or greater.
6. Where a special condition exists, including but not limited to, absence of adequate
construction plans; non- prescriptive structural design; fire resistive and means
of egress compliance; and alternative materials and methods of construction.
Exception:
The building official is authorized to waive the requirement for stamping by a registered
design professional if it is found that the nature of the work applied for is such
that stamping of construction documents is not required by law.
107.2 Construction documents. Construction documents shall be in accordance with sections 107.2.1 through 107.2.7.
Exception:
The building official is authorized to waive the submission of certain construction
documents or other items if determined to not be necessary to obtain code compliance
due to the nature of the work applied for.
107.2.1 Information on construction documents. Construction documents shall be drawn to scale, dimensioned and drawn on suitable
material. Electronic media documents are permitted to be submitted where approved
by the building official. Construction documents shall be of sufficient clarity to
indicate the exact location, nature and extent of the work proposed and show in detail
that it will conform to the provisions of this code and relevant laws, ordinances,
rules and regulations, as determined by the building official. The follow construction
plans shall be submitted when applying for a permit:
1. Plot and civil plans.
2. Floor plans.
3. Foundation plans.
4. Floor framing plans.
5. Roof framing plans.
6. Cross sections and construction details.
7. Exterior elevations.
8. Electrical, plumbing, mechanical plans.
9. Means of egress and fire wall plan.
10. For existing structures, existing and proposed plans.
11. Other information required by the Building Official.
107.2.2 Fire protection system shop drawings. Shop drawings for the fire protection system(s) shall be submitted to the Fire Prevention
Bureau or designated agency.
107.2.3 Means of egress and fire wall. The construction documents shall show in sufficient detail the location, construction,
size and character of all portions of the means of egress including the path of the
exit discharge to the public way in compliance with the provisions of this code. In
other than occupancies in Groups R-3, and U, the construction documents shall designate
the number of occupants to be accommodated on every floor, and in all rooms and spaces.
The plan shall also include the location and fire resistive rating of any Fire Wall
pursuant to this code.
107.2.4 Exterior wall envelope. Construction documents for all buildings shall describe the exterior wall envelope
in sufficient detail to determine compliance with this code. The construction documents
shall provide details of the exterior wall envelope as required, including flashing,
intersections with dissimilar materials, corners, end details, control joints, intersections
at roof, eaves or parapets, means of drainage, water-resistive membrane and details
around openings.
The construction documents shall include manufacturer's installation instructions
that provide supporting documentation that the proposed penetration and opening details
described in the construction documents maintain the weather resistance of the exterior
wall envelope. The supporting documentation shall fully describe the exterior wall
system that was tested, where applicable, as well as the test procedure used.
107.2.5 Exterior balconies and elevated walking surfaces. Where balconies or other elevated walking surfaces are exposed to water from direct
or blowing rain, snow, or irrigation, and the structural framing is protected by an
impervious moisture barrier, the construction documents shall include details for
all elements of the impervious moisture barrier system. The construction documents
shall include manufacturer's installation instructions.
107.2.6 Site plan. The construction documents submitted with the application for permit shall be accompanied
by a site plan with the property's Tax Map Key number and address and showing to scale
the size and location of new construction and existing structures on the site, distances
from lot lines, the established street grades and the proposed finished grades and,
as applicable, flood hazard areas, floodways, and design flood elevations; and it
shall be drawn in accordance with an accurate boundary line survey. In the case of
demolition, the site plan shall show construction to be demolished and the location
and size of existing structures and construction that are to remain on the site or
plot. The building official is authorized to waive or modify the requirement for a
site plan when the application for permit is for alteration or repair or when otherwise
warranted.
107.2.7 Structural information. The construction documents shall provide the information specified in chapter 16.
107.3 Examination of documents. The building official shall examine or cause to be examined the accompanying submittal
documents and shall ascertain by such examinations whether the construction indicated
and described is in accordance with the requirements of this code and other pertinent
laws or ordinances. This jurisdiction conducts non-structural building code reviews.
Structural design requirements shall be by prescriptive methods or engineered design
by the registered design professional.
107.3.1 Approval of construction documents. When the building official issues a permit, the construction documents shall be approved,
in writing or by stamp, as "APPROVED". The approved plans and specifications shall
not be changed modified to altered without authorizations from the building official,
and all work regulated by this code shall be done in accordance with the approved
plans. One set of construction documents so reviewed shall be retained by the building
official until construction has been completed and the building official has approved
the final inspection. Should there be any errors or omissions, the construction plans
and work shall be revised as required by the building official.
107.3.2 Phased approval. The building official is authorized to issue a permit for the construction of foundations
or any other part of a building or structure before the construction documents for
the whole building or structure have been submitted, provided that adequate information
and detailed statements have been filed complying with pertinent requirements of this
code. The holder of such permit for the foundation or other parts of a building or
structure shall proceed at the holder's own risk with the building operation and without
assurance that a permit for the entire structure will be granted.
107.3.3 Design professional in responsible charge. Where it is required that documents be prepared by a registered design professional,
the building official shall be authorized to require the owner or the owner's authorized
agent to engage and designate on the building permit application a registered design
professional who shall act as the registered design professional in responsible charge.
If the circumstances require, the owner or the owner's authorized agent shall designate
a substitute registered design professional in responsible charge who shall perform
all of the duties required of the original registered design professional in responsible
charge. The building official shall be notified in writing by the owner or the owner's
authorized agent if the registered design professional in responsible charge is changed
or is unable to continue to perform the duties.
The registered design professional in responsible charge shall be responsible for
reviewing and coordinating submittal documents prepared by others, including phased
and deferred submittal items, for compatibility with the design of the building or
structure.
107.3.4 Deferred submittals. For the purposes of this section, deferred submittals are defined as those portions
of the design that are not submitted at the time of the application and that are to
be submitted to the building official within a specified period.
Deferral of any submittal items shall have the prior approval of the building official.
The registered design professional in responsible charge shall list the deferred submittals
on the construction documents and shall submit the deferred submittal for review by
the building official.
Documents for deferred submittal items shall be submitted to the registered design
professional in responsible charge who shall review them and forward them to the building
official with a notation indicating that the deferred submittal documents have been
reviewed and been found to be in general conformance to the design of the building.
The deferred submittal items shall not be installed until the design and submittal
documents have been approved by the building official. The applicant shall pay additional
plan review fees, minimum two hours, as set forth in the annual budget ordinance.
107.4 Amended construction documents. Work shall be installed in accordance with the approved construction documents, and
any changes made during construction that are not in compliance with the approved
construction documents shall be resubmitted for approval as an amended set of construction
documents. The applicant shall pay additional plan review fees, minimum two hours,
as set forth in the annual budget ordinance. The building official can require a new
building permit.
107.5 Retention of construction documents. One set of approved construction documents shall be retained by the building official.
107.6 Design registration. Any architect or structural engineer may submit construction plans for a single-family
dwelling unit or for a detached or attached accessory dwelling unit complying to Maui
County Code, section 19.35 , to be registered with the building official as a model home. The architect or engineer
shall submit plans and other documents as required by the building official.
A. The filing fee to apply for design registration shall be as set forth in the annual
budget.
B. The building official may circulate the plans to other governmental agencies for
verification of compliance with other applicable regulations.
C. After the building official determines that the plans are in compliance with applicable
codes and regulations, the building official shall assign a registration number on
the approved plans, herein referred to as registered plans.
D. Codes and amendments adopted or enforced after registration approval may invalidate
such approval or be required to be recertified as determined by the building official.
E. The building permit applicant shall submit a completed building permit application
and a copy of a site plan stamped by the same architect or engineer who prepared the
registered plans, showing the location of the model home on the property with setback
distance, elevation contours, and other applicable information. The model home registration
number shall be noted on all building permit application submittals.
F. There shall be a plan review fee for registered designs as set forth in the annual
budget. If the registered design includes building design options, the highest value
of work shall be used. Other fees and assessments including, but not limited to, permit,
park assessment and sewerage fees shall be paid.
G. One revision to the registered plans may be approved by the building official if:
the exterior footprint of the model home has not been changed; the proposed revisions
are in compliance with the building code and other applicable codes, including any
amendments; the applicant pays additional plan review fees as set forth in the annual
budget ordinance; and the architect or engineer agrees to submit "as-built" construction
drawings immediately. Additional revisions may be allowed as determined by the building
official.
107.7 Errors and omissions. If there are any errors or omissions on any construction document, the registered
design professional and owner shall be responsible to make corrections promptly to
the satisfaction of the building official.
( Ord. No. 5507 , § 2, 2023)
SECTION 108 TEMPORARY STRUCTURES AND USES
Read the official text at library.municode.com ↗as published Nov 21, 2025our copy taken Aug 21, 2026
Published by the County of Maui through Municode.