Fast track permitting
Read the official text at library.municode.com ↗This section creates a fast track permitting process for residential workforce housing projects that meet certain qualifications. It sets deadlines for county departments to review permits and gives these projects priority. It also requires an annual report and allows rules to be adopted.
countiesdevelopers
The ordinance, as written (Maui County) — Fast track permitting
A copy, taken August 21, 2026. The version published by Maui County is the one that governs, and it may have changed since. Check it before relying on anything here.
A.
Purpose. The purpose of this section is to support the fast track development of residential
workforce housing by codifying the County's priority permitting policy for expediting
its permit process and giving priority to qualified residential workforce housing
projects.
B.
Project qualifications. A project comprised of 100 percent residential workforce housing
units with a fully-executed residential workforce housing agreement between the developer
and the County, recorded in the bureau of conveyances or registered in the land court,
in compliance with this chapter, shall be eligible for fast track permitting.
C.
Permits subject to fast track permitting. Qualified projects may utilize the fast
track permitting process to expedite the review and issuance of all County permits
necessary for the development of the project site, including subdivision applications,
civil construction plan permits, and other plans and permits associated with the development
of the project site. Building permits shall only be expedited for residential workforce
housing units.
Fast track permitting applies to applications that require review or approval by the
planning commissions, the council, or any other County board or commission. The processing
of fast track applications shall be given first priority by County departments while
complying with all statutory and procedural requirements.
D.
Fast track permitting processing procedure. All applicable County departments shall
review and process permits for qualified projects in accordance with state and county
laws. Applicable departments shall begin the permit review process for fast track
projects no later than two working days following submission of all required applications
and forms deemed complete. Applicable departments shall submit initial comments to
the applicant within fifteen working days following submission of all required applications
and forms deemed complete. If on the sixteenth working day an applicant does not receive
initial comments, the permit will be deemed approved by the applicable department.
Applicable departments shall begin the permit review process for qualified projects
before all other permit applications for projects not eligible for fast track permitting.
E.
Fast track applications requiring council review. For qualified projects subject to
fast track permitting, the council shall schedule the initial meeting for such application
within thirty days of the referral to the appropriate committee. The council shall
make its reasonable best efforts to approve or deny the application within sixty days
of the referral to committee.
F.
Annual report. The department shall prepare and submit an annual report to the council
on the following:
1.
The number of qualified projects that utilized the County's fast track permitting
process.
2.
The length of review time for each permit by each department.
G.
Rules. The director may adopt administrative rules to implement the fast track permitting
procedure provided for in this section or amend rules adopted to implement this chapter
to include fast track permitting.
( Ord. No. 4939 , § 2, 2018)
Read the official text at library.municode.com ↗as published Nov 21, 2025our copy taken Aug 21, 2026
Published by the County of Maui through Municode.
LawTrove is not legal advice. The summary above is a computer-generated restatement — the authoritative text is the official version linked above.