MCC §2.97.160

Deadlines for starting and finishing construction

Read the official text at library.municode.com ↗

This section sets deadlines for when a project must start and finish after the county approves it. The project must start within two years and be finished within five years. The county council can extend these deadlines, and the developer must work with the county on a bond to make sure the work is done on time.

developers

The ordinance, as written (Maui County) — Timing of completion

A copy, taken August 21, 2026. The version published by Maui County is the one that governs, and it may have changed since. Check it before relying on anything here.

Construction of the project shall be initiated within two years of the adoption of the resolution and shall be completed within five years of the adoption of the resolution. For purposes of this section, construction of the project shall be considered initiated when a building permit is issued and construction of a building has begun. Extensions may be allowed by council by resolutions. Upon commencement of construction, the developer shall work with the department of public works on a form of bonding to ensure that construction is completed within the designated timeframe. ( Ord. No. 4941 , § 1, 2018)
Read the official text at library.municode.com ↗as published Nov 21, 2025our copy taken Aug 21, 2026

Published by the County of Maui through Municode.