MCC §2.97.160
Deadlines for starting and finishing construction
Read the official text at library.municode.com ↗This section sets deadlines for when a project must start and finish after the county approves it. The project must start within two years and be finished within five years. The county council can extend these deadlines, and the developer must work with the county on a bond to make sure the work is done on time.
developers
The ordinance, as written (Maui County) — Timing of completion
A copy, taken August 21, 2026. The version published by Maui County is the one that governs, and it may have changed since. Check it before relying on anything here.
Construction of the project shall be initiated within two years of the adoption of
the resolution and shall be completed within five years of the adoption of the resolution.
For purposes of this section, construction of the project shall be considered initiated
when a building permit is issued and construction of a building has begun. Extensions
may be allowed by council by resolutions. Upon commencement of construction, the developer
shall work with the department of public works on a form of bonding to ensure that
construction is completed within the designated timeframe.
( Ord. No. 4941 , § 1, 2018)
Read the official text at library.municode.com ↗as published Nov 21, 2025our copy taken Aug 21, 2026
Published by the County of Maui through Municode.
LawTrove is not legal advice. The summary above is a computer-generated restatement — the authoritative text is the official version linked above.