This section explains the first steps for a proposed public improvement, like roads or sewers. The council asks the mayor to have the director study the project and write a preliminary report. The report must cover costs, boundaries, and who pays. It is shared with neighborhood boards, and water system plans are included if needed.

courts

The ordinance, as written (Honolulu County) — Initial procedure

A copy, taken August 22, 2026. The version published by Honolulu is the one that governs, and it may have changed since. Check it before relying on anything here.

(a) The council shall, by resolution, request the mayor to direct the director to investigate and prepare a preliminary report to the council that shall include: (1) Preliminary data concerning the highways, sanitary sewer system, storm drainage system, water system, sidewalk, street lighting system, or other public facility or improvement proposed to be opened or improved; (2) The general character and extent of improvements proposed to be opened or improved; (3) Whether such improvements may be assessed on a frontage or area basis, or some other method or basis of assessment; (4) Whether it will be necessary to acquire any new land, the estimated cost of acquiring any such land and the proportion of such cost that may be borne by the city; (5) The materials recommended to meet the conditions of the improvements; (6) The boundaries of the improvement district to be proposed and any subdistricts or zones therein as to which different portions of the cost may be charged; (7) The estimated cost of the improvements; (8) The portions of the cost to be borne by the city; and (9) The portions of the cost to be specifically assessed against the land specially benefitted, with the estimated total amount of assessment to be made against each property according to the method of assessment proposed. Further, such resolution shall request the mayor to direct the director to prepare and furnish all necessary preliminary surveys, maps, plans, drawings and other data, details and specifications for the improvements and any other matters intended to apply thereto. (b) The preliminary report, when so furnished and filed with the council, shall also be provided to the neighborhood board or boards, if any, in the area included within the proposed improvement district, and the director, or the director’s representative, shall make a presentation to the board, or boards, on the proposed improvement district. (c) If the work proposed to be done includes the improvement of a water system or the laying or installation of conduits, pipes, hydrants, or any appliance for supplying or distributing a water supply, the director shall obtain from the board of water supply preliminary plans and estimates for such proposed water system. The director shall then furnish the board of water supply with preliminary plans of the proposed improvements that will enable the board of water supply to make its plans and estimates for the proposed water system. The director shall incorporate such preliminary plans and estimates of the board of water supply in the director’s preliminary report to the council. )
Read the official text at honolulu.gov ↗as published Jan 1, 2026our copy taken Aug 22, 2026

Published by the City and County of Honolulu through American Legal Publishing.