ROH §18-4.2

What plans and documents you must submit with a building permit

Read the official text at honolulu.gov ↗

When you apply for a building permit, you must submit three sets of plans and other documents, and leave one set with the state health department. The building official can waive these requirements for simple work, and some repairs or small homes have fewer rules. Licensed professionals must prepare plans for work affecting public safety or health, and for tall retaining walls.

buyerscontractorsdevelopershomeownerslandowners

The ordinance, as written (Honolulu County) — Plans, specifications, and other data

A copy, taken August 22, 2026. The version published by Honolulu is the one that governs, and it may have changed since. Check it before relying on anything here.

(a) With each application for a building permit, three sets of plans, specifications, calculations, construction inspection requirements, and other data shall be submitted. One set of plans shall be submitted to and left with the State department of health. Construction inspection requirements are as defined in § 18-4.6 . Exception: the building official may waive the submission of plans, specifications, calculations, construction inspection requirements, etc., if the building official finds that the nature of the work applied for is such that reviewing of plans is not necessary to obtain compliance with this code. (b) No plans or specifications are required for repair or replacement work, unless requested by the building official. (c) Plans for single- or two-family dwellings are not required to show plumbing piping plans or diagrams unless requested by the building official. (d) All plans and specifications relating to work that affects the public safety or health and for which a building permit is required shall be prepared by or under the supervision of a duly licensed professional engineer or architect as required by HRS Chapter 464. (e) All plans for retaining walls 5 feet or more in height shall be prepared, designed, or approved by a duly licensed architect or engineer in the structural or civil branches. (f) Electrical plans and specifications shall bear the approval of either a duly licensed electrical engineer, or a duly licensed architect or engineer qualified in such work by experience; provided that if the demand load of the proposed installation is less than 30 kilovolt-amperes, the approval of an engineer or architect shall be required only if the building official so directs. )
Read the official text at honolulu.gov ↗as published Jan 1, 2026our copy taken Aug 22, 2026

Published by the City and County of Honolulu through American Legal Publishing.

LawTrove is not legal advice. The summary above is a computer-generated restatement — the authoritative text is the official version linked above.